Levine Building project timeline

Levine Building project detailed timeline
February 2019 Tree removal from the Levine Building site
March 2019 Temporary building starts to be installed on the North Lawn (to replace Danson and Britton Rooms and provide temporary study space)
May 2019 Temporary building is completed and ready for use
July 2019 Enabling works start around the War Memorial Library and gardening facilities
August 2019 Start of demolition works to the Cumberbatch Building
November 2019 Further archaeological investigation to site in preparation for groundworks
January 2020 Construction begins on Levine Building
Summer 2021 Construction completed on Levine Building
Summer 2021 Temporary building is converted to allow accommodation for kitchen and hall refurbishment
Michaelmas 2021 Levine Building is ready for occupation